San Mateo County · ADU permit data · Updated 2026-10-20

How long does an ADU permit take in Menlo Park?

75permits a year ADU building permits, 2023–2025 average

Bay Area
6.0 mo
Status
Not comparable
Rank
unranked

We cannot publish a reliable wait time for Menlo Park. Menlo Park reports the same date for the application and the permit on 59% of matched ADUs, so its wait time cannot be compared with other cities. We leave it out of the ranking.

State limit
60 days
Bay Area
6.0 mo
months
Months from application to ADU permit, 2023–2025, drawn to one scale. The state's 60-day clock starts once an application is complete.

Months from ADU application to building permit

Bay Area figures for reference. Menlo Park reports the same date for the application and the permit on 59% of matched ADUs, so its wait time cannot be compared with other cities. We leave it out of the ranking.

Source: California HCD Annual Progress Reports, filed by the City of Menlo Park

Estimate my dates

Fast quarter, median and slow quarter, in months

San Mateo County

Bay Area 3.8–10.5 mo

Median Fast quarter to slow quarter

Median wait

  • San Mateo County 7.0 mo
  • Bay Area 6.0 mo
  • Atherton fastest nearby 3.4 mo
  • Half Moon Bay slowest nearby 15.9 mo

Median wait in the 52 ranked cities

Other ranked cities Bay Area 6.0

Bay Area

6.0months

median of 5,578 matched Bay Area permits, 2023–2025

Permits issued

226 ADU permits, 2023–2025

ADU building permits issued and ADUs finished, by year

Source: units by calendar year, as reported by the City of Menlo Park to California HCD

Menlo Park, units per year

0 45 90 2018: 15 Permits issued2019: 4 Permits issued2020: 13 Permits issued2021: 36 Permits issued2022: 56 Permits issued2023: 89 Permits issued2024: 76 Permits issued2025: 61 Permits issued 2018: 10 ADUs completed2019: 7 ADUs completed2020: 7 ADUs completed2021: 17 ADUs completed2022: 27 ADUs completed2023: 40 ADUs completed2024: 37 ADUs completed2025: 33 ADUs completed 61 Permits issued 33 ADUs completed 20182020202220242025

ADU permits a year, 2023–2025 average

ADU permits a year per 1,000 houses, 109 places

Menlo Park 10.4

Menlo Park Other Bay Area places

Menlo Park

75a year

ADU permits, 2023–2025 average

Share of new homes that are ADUs

Of every home Menlo Park permitted in 2023–2025, this share was an ADU.

Source: HCD Annual Progress Reports, 2023–2025

Menlo Park

59%

ADU permits per 1,000 houses

Permits a year for every 1,000 detached houses, so small and large cities can be compared.

Source: HCD Annual Progress Reports; DOF housing estimates

Menlo Park

10.4

rank 3 of 92

Change since 2019–2021

Yearly ADU permits in 2023–2025, up 326% from 2019–2021.

Source: HCD Annual Progress Reports

Menlo Park

+326%

Build time

94 finished ADUs

Building permit to finished ADU

Median time from building permit to certificate of occupancy for ADUs finished in 2023–2025. Add it to the permit wait for a full timeline.

Source: HCD Annual Progress Reports, 2023–2025

Menlo Park

11.6months

median of 94

Slow quarter of builds took longer than

One ADU in four took longer than this to reach a certificate of occupancy after the permit.

Source: HCD Annual Progress Reports, 2023–2025, 75th percentile

Menlo Park

14.6months

Months from ADU application to building permit

Median Fast quarter to slow quarter Bay Area median, 6.0 months Number is the rank out of 52 cities

06121824
median
  1. 8Atherton
    3.4
  2. 21Hillsborough
    5.3
  3. 27Belmont
    6.0
  4. 32San Carlos
    6.3
  5. 35Unincorporated San Mateo County
    7.0
  6. 47East Palo Alto
    8.6
  7. 49Burlingame
    9.1
  8. 52Half Moon Bay
    15.9

Planning an ADU in Menlo Park

  1. 1 After the permit, ADUs here took a median of 11.6 months to reach a certificate of occupancy (Bay Area: 13.0).
  2. 2 Menlo Park permits about 75 ADUs a year, up 326% from 2019–2021. Local designers and builders have recent examples to show you; ask for permitted ADUs in Menlo Park, not elsewhere.
  3. 3 The part of the wait you control is the first submission. Complete drawings, a site plan that matches the survey, and answers to the city's ADU checklist cut down on correction rounds.
  4. Read next: why home plans get sent back · permit drawings vs. full plans · architect fee calculator

Timeline tool

When would your permit come through?

Pick a start date and see the fast, likely and slow dates for Menlo Park, from the numbers on this page.

Estimate my permit dates

Next step

Not sure who to call first?

Answer a few questions about your lot and your plans. We point you to the right kind of help for an ADU in Menlo Park: an architect, a permit-drawing team, or a design-build firm. About two minutes, no call list.

Find the right first call

Start with the city's own rules: ADU rules and process.

Sheet
C-146
Drawing
ADU permit record, Menlo Park
Date
2026-10-20
Scale
Not to scale

Source: Bay Area ADU Permit Clock 2026, our analysis of the California HCD Housing Element Annual Progress Reports (data.ca.gov) filed by the City of Menlo Park, and DOF housing estimates. Wait times are matched on parcel number and include applicant revision time. The 60-day rule is in Government Code section 66317. How we measured it · See all 109 jurisdictions

Common questions

How long does it take to get an ADU permit in Menlo Park?

There are not enough comparable records to give a reliable number for Menlo Park. Across the Bay Area the median was 6.0 months.

How many ADUs does Menlo Park approve?

Menlo Park issued 226 ADU building permits in 2023–2025, about 75 a year. ADUs were 59% of all new homes permitted there.

How long does it take to build an ADU in Menlo Park?

The median time from building permit to certificate of occupancy was 11.6 months for ADUs completed in 2023–2025.