Share of new homes that are ADUs
Of every home Menlo Park permitted in 2023–2025, this share was an ADU.
Source: HCD Annual Progress Reports, 2023–2025
Menlo Park
59%
San Mateo County · ADU permit data · Updated 2026-10-20
75permits a year ADU building permits, 2023–2025 average
We cannot publish a reliable wait time for Menlo Park. Menlo Park reports the same date for the application and the permit on 59% of matched ADUs, so its wait time cannot be compared with other cities. We leave it out of the ranking.
Bay Area figures for reference. Menlo Park reports the same date for the application and the permit on 59% of matched ADUs, so its wait time cannot be compared with other cities. We leave it out of the ranking.
Source: California HCD Annual Progress Reports, filed by the City of Menlo Park
Fast quarter, median and slow quarter, in months
San Mateo County
Bay Area 3.8–10.5 mo
Median Fast quarter to slow quarter
Median wait
Median wait in the 52 ranked cities
Other ranked cities Bay Area 6.0
Bay Area
6.0months
median of 5,578 matched Bay Area permits, 2023–2025
Source: units by calendar year, as reported by the City of Menlo Park to California HCD
Menlo Park, units per year
ADU permits a year, 2023–2025 average
ADU permits a year per 1,000 houses, 109 places
Menlo Park Other Bay Area places
Menlo Park
75a year
ADU permits, 2023–2025 average
Of every home Menlo Park permitted in 2023–2025, this share was an ADU.
Source: HCD Annual Progress Reports, 2023–2025
Menlo Park
59%
Permits a year for every 1,000 detached houses, so small and large cities can be compared.
Source: HCD Annual Progress Reports; DOF housing estimates
Menlo Park
10.4
rank 3 of 92
Yearly ADU permits in 2023–2025, up 326% from 2019–2021.
Source: HCD Annual Progress Reports
Menlo Park
+326%
Median time from building permit to certificate of occupancy for ADUs finished in 2023–2025. Add it to the permit wait for a full timeline.
Source: HCD Annual Progress Reports, 2023–2025
Menlo Park
11.6months
median of 94
One ADU in four took longer than this to reach a certificate of occupancy after the permit.
Source: HCD Annual Progress Reports, 2023–2025, 75th percentile
Menlo Park
14.6months
Median Fast quarter to slow quarter Bay Area median, 6.0 months Number is the rank out of 52 cities
Every page in San Mateo County: median wait where we can measure it, otherwise ADU permits a year
Timeline tool
Pick a start date and see the fast, likely and slow dates for Menlo Park, from the numbers on this page.
Estimate my permit datesNext step
Answer a few questions about your lot and your plans. We point you to the right kind of help for an ADU in Menlo Park: an architect, a permit-drawing team, or a design-build firm. About two minutes, no call list.
Find the right first callStart with the city's own rules: ADU rules and process.
Source: Bay Area ADU Permit Clock 2026, our analysis of the California HCD Housing Element Annual Progress Reports (data.ca.gov) filed by the City of Menlo Park, and DOF housing estimates. Wait times are matched on parcel number and include applicant revision time. The 60-day rule is in Government Code section 66317. How we measured it · See all 109 jurisdictions
There are not enough comparable records to give a reliable number for Menlo Park. Across the Bay Area the median was 6.0 months.
Menlo Park issued 226 ADU building permits in 2023–2025, about 75 a year. ADUs were 59% of all new homes permitted there.
The median time from building permit to certificate of occupancy was 11.6 months for ADUs completed in 2023–2025.