Contra Costa County · ADU permit data · Updated 2026-10-20

How long does an ADU permit take in Richmond?

8.0months median, application to building permit, 2023–2025

Bay Area
6.0 mo
Slow quarter
14.6+ mo
Rank
41 of 52

That is 32% longer than the Bay Area median of 6.0 months. One in four applicants waited more than 14.6 months.

State limit
60 days
Richmond
8.0 mo
Bay Area
6.0 mo
months
Months from application to ADU permit, 2023–2025, drawn to one scale. The state's 60-day clock starts once an application is complete.

Months from ADU application to building permit

ADUs permitted in 2023–2025, 72 matched on parcel number. Includes time owners spent revising plans.

Source: California HCD Annual Progress Reports, filed by the City of Richmond

Estimate my dates

Fast quarter, median and slow quarter, in months

Richmond 5.7–14.6 mo

Contra Costa County

Bay Area 3.8–10.5 mo

Median Fast quarter to slow quarter

Median wait

  • Richmond 8.0 mo
  • Contra Costa County 5.5 mo
  • Bay Area 6.0 mo
  • Pleasant Hill fastest nearby 1.5 mo
  • San Pablo slowest nearby 10.4 mo

Where Richmond sits among 52 ranked cities

Richmond 8.0

Richmond Other ranked cities Bay Area 6.0

Richmond

8.0months

median wait, 2023–2025

Took longer than 60 days

State law gives the city 60 days to act once an application is complete. Counted from first submission, this share of ADUs took longer. Ask for the completeness letter, which is due within 15 business days, and keep its date.

Source: HCD Annual Progress Reports, 2023–2025; Gov. Code 66317

Richmond

97%

of matched ADUs

Slow quarter waited longer than

One applicant in four took longer than this. Plan on it if the city sends your plans back for another round of corrections.

Source: HCD Annual Progress Reports, 2023–2025, 75th percentile

Richmond

14.6months

Fast quarter had a permit within

One applicant in four had a building permit within this time from first submission.

Source: HCD Annual Progress Reports, 2023–2025, 25th percentile

Richmond

5.7months

Permits issued

200 ADU permits, 2023–2025

ADU building permits issued and ADUs finished, by year

Source: units by calendar year, as reported by the City of Richmond to California HCD

Richmond, units per year

0 42.5 85 2018: 48 Permits issued2019: 39 Permits issued2020: 42 Permits issued2021: 75 Permits issued2022: 55 Permits issued2023: 85 Permits issued2024: 54 Permits issued2025: 61 Permits issued 2018: 11 ADUs completed2019: 26 ADUs completed2020: 34 ADUs completed2021: 20 ADUs completed2022: 31 ADUs completed2023: 46 ADUs completed2024: 47 ADUs completed2025: 35 ADUs completed 61 Permits issued 35 ADUs completed 20182020202220242025

ADU permits a year, 2023–2025 average

ADU permits a year per 1,000 houses, 109 places

Richmond 2.9

Richmond Other Bay Area places

Richmond

67a year

ADU permits, 2023–2025 average

Share of new homes that are ADUs

Of every home Richmond permitted in 2023–2025, this share was an ADU.

Source: HCD Annual Progress Reports, 2023–2025

Richmond

60%

ADU permits per 1,000 houses

Permits a year for every 1,000 detached houses, so small and large cities can be compared.

Source: HCD Annual Progress Reports; DOF housing estimates

Richmond

2.9

rank 40 of 92

Change since 2019–2021

Yearly ADU permits in 2023–2025, up 28% from 2019–2021.

Source: HCD Annual Progress Reports

Richmond

+28%

Build time

98 finished ADUs

Building permit to finished ADU

Median time from building permit to certificate of occupancy for ADUs finished in 2023–2025. Add it to the permit wait for a full timeline.

Source: HCD Annual Progress Reports, 2023–2025

Richmond

16.1months

median of 98

Slow quarter of builds took longer than

One ADU in four took longer than this to reach a certificate of occupancy after the permit.

Source: HCD Annual Progress Reports, 2023–2025, 75th percentile

Richmond

24.2months

Months from ADU application to building permit

Median Fast quarter to slow quarter Bay Area median, 6.0 months Number is the rank out of 52 cities

06121824
median
  1. 1Pleasant Hill
    1.5
  2. 3Oakley
    3.0
  3. 11Concord
    4.3
  4. 17El Cerrito
    4.8
  5. 20Walnut Creek
    5.3
  6. 28Lafayette
    6.2
  7. 30Unincorporated Contra Costa County
    6.2
  8. 41Richmond
    8.0
  9. 50San Pablo
    10.4

Planning an ADU in Richmond

  1. 1 State law gives the city 60 days to act once your application is complete. Counting from first submission, 97% of ADUs here took longer than 60 days to reach an issued permit (Bay Area: 93%). Ask for the completeness letter, which the city owes you within 15 business days, and keep its date.
  2. 2 Plan for about 8.0 months to get your permit, and up to 14.6 if the city sends your plans back for another round. Those numbers include the time owners spent revising drawings.
  3. 3 After the permit, ADUs here took a median of 16.1 months to reach a certificate of occupancy (Bay Area: 13.0).
  4. 4 Richmond permits about 67 ADUs a year, up 28% from 2019–2021. Local designers and builders have recent examples to show you; ask for permitted ADUs in Richmond, not elsewhere.
  5. 5 The part of the wait you control is the first submission. Complete drawings, a site plan that matches the survey, and answers to the city's ADU checklist cut down on correction rounds.
  6. Read next: why home plans get sent back · permit drawings vs. full plans · architect fee calculator

Timeline tool

When would your permit come through?

Pick a start date and see the fast, likely and slow dates for Richmond, from the numbers on this page.

Estimate my permit dates

Next step

Not sure who to call first?

Answer a few questions about your lot and your plans. We point you to the right kind of help for an ADU in Richmond: an architect, a permit-drawing team, or a design-build firm. About two minutes, no call list.

Find the right first call

Start with the city's own rules: ADU rules and process.

Sheet
C-170
Drawing
ADU permit record, Richmond
Date
2026-10-20
Scale
Not to scale

Source: Bay Area ADU Permit Clock 2026, our analysis of the California HCD Housing Element Annual Progress Reports (data.ca.gov) filed by the City of Richmond, and DOF housing estimates. Wait times are matched on parcel number and include applicant revision time. The 60-day rule is in Government Code section 66317. How we measured it · See all 109 jurisdictions

Common questions

How long does it take to get an ADU permit in Richmond?

For ADUs permitted in 2023–2025, the median time from application to building permit in Richmond was 8.0 months (244 days), based on 72 permits we could match. A quarter took longer than 14.6 months.

How many ADUs does Richmond approve?

Richmond issued 200 ADU building permits in 2023–2025, about 67 a year. ADUs were 60% of all new homes permitted there.

How long does it take to build an ADU in Richmond?

The median time from building permit to certificate of occupancy was 16.1 months for ADUs completed in 2023–2025.