How long does an ADU permit take in Santa Rosa?

6.4months median, application to building permit, 2023–2025

Bay Area
6.0 mo
Slow quarter
10.2+ mo
Rank
34 of 52

That is about the same as the Bay Area median of 6.0 months. One in four applicants waited more than 10.2 months.

State limit
60 days
Santa Rosa
6.4 mo
Bay Area
6.0 mo
months
Months from application to ADU permit, 2023–2025, drawn to one scale. The state's 60-day clock starts once an application is complete.

Months from ADU application to building permit

ADUs permitted in 2023–2025, 89 matched on parcel number. Includes time owners spent revising plans.

Source: California HCD Annual Progress Reports, filed by the City of Santa Rosa

Estimate my dates

Fast quarter, median and slow quarter, in months

Santa Rosa 3.6–10.2 mo

Sonoma County

Bay Area 3.8–10.5 mo

Median Fast quarter to slow quarter

Median wait

Where Santa Rosa sits among 52 ranked cities

Santa Rosa 6.4

Santa Rosa Other ranked cities Bay Area 6.0

Santa Rosa

6.4months

median wait, 2023–2025

Took longer than 60 days

State law gives the city 60 days to act once an application is complete. Counted from first submission, this share of ADUs took longer. Ask for the completeness letter, which is due within 15 business days, and keep its date.

Source: HCD Annual Progress Reports, 2023–2025; Gov. Code 66317

Santa Rosa

91%

of matched ADUs

Slow quarter waited longer than

One applicant in four took longer than this. Plan on it if the city sends your plans back for another round of corrections.

Source: HCD Annual Progress Reports, 2023–2025, 75th percentile

Santa Rosa

10.2months

Fast quarter had a permit within

One applicant in four had a building permit within this time from first submission.

Source: HCD Annual Progress Reports, 2023–2025, 25th percentile

Santa Rosa

3.6months

Permits issued

238 ADU permits, 2023–2025

ADU building permits issued and ADUs finished, by year

Source: units by calendar year, as reported by the City of Santa Rosa to California HCD

Santa Rosa, units per year

0 75 150 2018: 79 Permits issued2019: 47 Permits issued2020: 63 Permits issued2021: 88 Permits issued2022: 101 Permits issued2023: 120 Permits issued2024: 71 Permits issued2025: 47 Permits issued 2018: 15 ADUs completed2019: 37 ADUs completed2020: 47 ADUs completed2021: 30 ADUs completed2022: 65 ADUs completed2023: 1 ADUs completed2024: 2 ADUs completed2025: 106 ADUs completed 47 Permits issued 106 ADUs completed 20182020202220242025

ADU permits a year, 2023–2025 average

ADU permits a year per 1,000 houses, 109 places

Santa Rosa 1.9

Santa Rosa Other Bay Area places

Santa Rosa

79a year

ADU permits, 2023–2025 average

Share of new homes that are ADUs

Of every home Santa Rosa permitted in 2023–2025, this share was an ADU.

Source: HCD Annual Progress Reports, 2023–2025

Santa Rosa

13%

ADU permits per 1,000 houses

Permits a year for every 1,000 detached houses, so small and large cities can be compared.

Source: HCD Annual Progress Reports; DOF housing estimates

Santa Rosa

1.9

rank 71 of 92

Change since 2019–2021

Yearly ADU permits in 2023–2025, up 20% from 2019–2021.

Source: HCD Annual Progress Reports

Santa Rosa

+20%

Build time

44 finished ADUs

Building permit to finished ADU

Median time from building permit to certificate of occupancy for ADUs finished in 2023–2025. Add it to the permit wait for a full timeline.

Source: HCD Annual Progress Reports, 2023–2025

Santa Rosa

12.5months

median of 44

Slow quarter of builds took longer than

One ADU in four took longer than this to reach a certificate of occupancy after the permit.

Source: HCD Annual Progress Reports, 2023–2025, 75th percentile

Santa Rosa

19.8months

Months from ADU application to building permit

Median Fast quarter to slow quarter Bay Area median, 6.0 months Number is the rank out of 52 cities

06121824
median
  1. 12Unincorporated Sonoma County
    4.3
  2. 34Santa Rosa
    6.4

Planning an ADU in Santa Rosa

  1. 1 State law gives the city 60 days to act once your application is complete. Counting from first submission, 91% of ADUs here took longer than 60 days to reach an issued permit (Bay Area: 93%). Ask for the completeness letter, which the city owes you within 15 business days, and keep its date.
  2. 2 Plan for about 6.4 months to get your permit, and up to 10.2 if the city sends your plans back for another round. Those numbers include the time owners spent revising drawings.
  3. 3 After the permit, ADUs here took a median of 12.5 months to reach a certificate of occupancy (Bay Area: 13.0).
  4. 4 Santa Rosa permits about 79 ADUs a year, up 20% from 2019–2021. Local designers and builders have recent examples to show you; ask for permitted ADUs in Santa Rosa, not elsewhere.
  5. 5 The part of the wait you control is the first submission. Complete drawings, a site plan that matches the survey, and answers to the city's ADU checklist cut down on correction rounds.
  6. Read next: why home plans get sent back · permit drawings vs. full plans · architect fee calculator

Timeline tool

When would your permit come through?

Pick a start date and see the fast, likely and slow dates for Santa Rosa, from the numbers on this page.

Estimate my permit dates

Next step

Not sure who to call first?

Answer a few questions about your lot and your plans. We point you to the right kind of help for an ADU in Santa Rosa: an architect, a permit-drawing team, or a design-build firm. About two minutes, no call list.

Find the right first call

Start with the city's own rules: City ADU page.

Sheet
C-185
Drawing
ADU permit record, Santa Rosa
Date
2026-10-20
Scale
Not to scale

Source: Bay Area ADU Permit Clock 2026, our analysis of the California HCD Housing Element Annual Progress Reports (data.ca.gov) filed by the City of Santa Rosa, and DOF housing estimates. Wait times are matched on parcel number and include applicant revision time. The 60-day rule is in Government Code section 66317. How we measured it · See all 109 jurisdictions

Common questions

How long does it take to get an ADU permit in Santa Rosa?

For ADUs permitted in 2023–2025, the median time from application to building permit in Santa Rosa was 6.4 months (194 days), based on 89 permits we could match. A quarter took longer than 10.2 months.

How many ADUs does Santa Rosa approve?

Santa Rosa issued 238 ADU building permits in 2023–2025, about 79 a year. ADUs were 13% of all new homes permitted there.

How long does it take to build an ADU in Santa Rosa?

The median time from building permit to certificate of occupancy was 12.5 months for ADUs completed in 2023–2025.