How long does an ADU permit take in Saratoga?

8.3months median, application to building permit, 2023–2025

Bay Area
6.0 mo
Slow quarter
12.4+ mo
Rank
44 of 52

That is 37% longer than the Bay Area median of 6.0 months. One in four applicants waited more than 12.4 months.

State limit
60 days
Saratoga
8.3 mo
Bay Area
6.0 mo
months
Months from application to ADU permit, 2023–2025, drawn to one scale. The state's 60-day clock starts once an application is complete.

Months from ADU application to building permit

ADUs permitted in 2023–2025, 90 matched on parcel number. Includes time owners spent revising plans.

Source: California HCD Annual Progress Reports, filed by the City of Saratoga

Estimate my dates

Fast quarter, median and slow quarter, in months

Saratoga 4.7–12.4 mo

Santa Clara County

Bay Area 3.8–10.5 mo

Median Fast quarter to slow quarter

Median wait

  • Saratoga 8.3 mo
  • Santa Clara County 6.0 mo
  • Bay Area 6.0 mo
  • Sunnyvale fastest nearby 4.6 mo
  • Santa Clara slowest nearby 8.4 mo

Where Saratoga sits among 52 ranked cities

Saratoga 8.3

Saratoga Other ranked cities Bay Area 6.0

Saratoga

8.3months

median wait, 2023–2025

Took longer than 60 days

State law gives the city 60 days to act once an application is complete. Counted from first submission, this share of ADUs took longer. Ask for the completeness letter, which is due within 15 business days, and keep its date.

Source: HCD Annual Progress Reports, 2023–2025; Gov. Code 66317

Saratoga

98%

of matched ADUs

Slow quarter waited longer than

One applicant in four took longer than this. Plan on it if the city sends your plans back for another round of corrections.

Source: HCD Annual Progress Reports, 2023–2025, 75th percentile

Saratoga

12.4months

Fast quarter had a permit within

One applicant in four had a building permit within this time from first submission.

Source: HCD Annual Progress Reports, 2023–2025, 25th percentile

Saratoga

4.7months

Permits issued

268 ADU permits, 2023–2025

ADU building permits issued and ADUs finished, by year

Source: units by calendar year, as reported by the City of Saratoga to California HCD

Saratoga, units per year

0 75 150 2018: 16 Permits issued2019: 24 Permits issued2020: 43 Permits issued2021: 65 Permits issued2022: 46 Permits issued2023: 77 Permits issued2024: 74 Permits issued2025: 117 Permits issued 2018: 0 ADUs completed2019: 4 ADUs completed2020: 0 ADUs completed2021: 0 ADUs completed2022: 0 ADUs completed2023: 0 ADUs completed2024: 0 ADUs completed2025: 0 ADUs completed 117 Permits issued 0 ADUs completed 20182020202220242025

ADU permits a year, 2023–2025 average

ADU permits a year per 1,000 houses, 109 places

Saratoga 9.3

Saratoga Other Bay Area places

Saratoga

89a year

ADU permits, 2023–2025 average

Share of new homes that are ADUs

Of every home Saratoga permitted in 2023–2025, this share was an ADU.

Source: HCD Annual Progress Reports, 2023–2025

Saratoga

60%

ADU permits per 1,000 houses

Permits a year for every 1,000 detached houses, so small and large cities can be compared.

Source: HCD Annual Progress Reports; DOF housing estimates

Saratoga

9.3

rank 5 of 92

Change since 2019–2021

Yearly ADU permits in 2023–2025, up 103% from 2019–2021.

Source: HCD Annual Progress Reports

Saratoga

+103%

Build time

Building permit to finished ADU

Too few finished ADUs here have matching permit dates to give a number. The Bay Area median is shown for reference.

Source: HCD Annual Progress Reports, 2023–2025

Bay Area

13.0months

median of 7,223

Months from ADU application to building permit

Median Fast quarter to slow quarter Bay Area median, 6.0 months Number is the rank out of 52 cities

06121824
median
  1. 15Sunnyvale
    4.6
  2. 19Palo Alto
    5.1
  3. 22Mountain View
    5.4
  4. 24San Jose
    5.4
  5. 31Milpitas
    6.2
  6. 33Los Gatos
    6.3
  7. 37Los Altos
    7.2
  8. 40Campbell
    7.8
  9. 43Unincorporated Santa Clara County
    8.2
  10. 44Saratoga
    8.3
  11. 46Santa Clara
    8.4

Planning an ADU in Saratoga

  1. 1 State law gives the city 60 days to act once your application is complete. Counting from first submission, 98% of ADUs here took longer than 60 days to reach an issued permit (Bay Area: 93%). Ask for the completeness letter, which the city owes you within 15 business days, and keep its date.
  2. 2 Plan for about 8.3 months to get your permit, and up to 12.4 if the city sends your plans back for another round. Those numbers include the time owners spent revising drawings.
  3. 3 Saratoga permits about 89 ADUs a year, up 103% from 2019–2021. Local designers and builders have recent examples to show you; ask for permitted ADUs in Saratoga, not elsewhere.
  4. 4 The part of the wait you control is the first submission. Complete drawings, a site plan that matches the survey, and answers to the city's ADU checklist cut down on correction rounds.
  5. Read next: why home plans get sent back · permit drawings vs. full plans · architect fee calculator

Timeline tool

When would your permit come through?

Pick a start date and see the fast, likely and slow dates for Saratoga, from the numbers on this page.

Estimate my permit dates

Next step

Not sure who to call first?

Answer a few questions about your lot and your plans. We point you to the right kind of help for an ADU in Saratoga: an architect, a permit-drawing team, or a design-build firm. About two minutes, no call list.

Find the right first call

Start with the city's own rules: ADU information.

Sheet
C-186
Drawing
ADU permit record, Saratoga
Date
2026-10-20
Scale
Not to scale

Source: Bay Area ADU Permit Clock 2026, our analysis of the California HCD Housing Element Annual Progress Reports (data.ca.gov) filed by the City of Saratoga, and DOF housing estimates. Wait times are matched on parcel number and include applicant revision time. The 60-day rule is in Government Code section 66317. How we measured it · See all 109 jurisdictions

Common questions

How long does it take to get an ADU permit in Saratoga?

For ADUs permitted in 2023–2025, the median time from application to building permit in Saratoga was 8.3 months (252 days), based on 90 permits we could match. A quarter took longer than 12.4 months.

How many ADUs does Saratoga approve?

Saratoga issued 268 ADU building permits in 2023–2025, about 89 a year. ADUs were 60% of all new homes permitted there.

How long does it take to build an ADU in Saratoga?

There are too few completed ADUs with matching permit dates to say. The Bay Area median was 13.0 months from permit to completion.